Task |
RAD |
| 11. User Design (for RAD): | |
| A11.1 Produce detailed system area model: | |
| A11.1.1 Complete entity relationship diagram |
R |
| A11.1.2 Complete process model |
R |
| A11.1.3 Perform interaction analysis |
O; TPM |
| A11.1.4 Confirm system area model |
R |
| A11.1.5 Develop clustered process/entity type matrix |
R |
| A11.2 Develop outline system design: | |
| A11.2.1 Define system procedures |
R |
| A11.2.2 Identify reusable design structures |
O; TPM |
| A11.2.3 Design system structure |
R |
| A11.2.4 Design screen/report layouts |
R |
| A11.2.5 Identify implementation requirements |
R |
| A11.2.6 Identify open issues |
R |
| A11.3 Refine system design: | |
| A11.3.1 Confirm consistency and completeness of system area model |
O; TPM & BPM |
| A11.3.2 Develop preliminary data structure |
R |
| A11.3.3 Develop prototypes |
R |
| A11.4 Prepare implementation plan: | |
| A11.4.1 Estimate construction effort |
R |
| A11.4.2 Finalize construction approach |
R |
| A11.4.3 Develop testing strategy |
R |
| A11.4.4 Develop implementation plan |
R |
| A11.5 Finalize system design: | |
| A11.5.1 Resolve open design issues |
R |
| A11.5.2 Discuss suggested design improvements |
O; TPM & BPM |
| A11.5.3 Review implementation plan |
O; TPM & BPM |
| A11.6 Obtain approval for construction: | |
| A11.6.1 Incorporate final JAD workshop results |
R |
| A11.6.2 Obtain approval to proceed |
R |
Rapid Application Development (RAD) Path
Next : Rapid Construction Matrix
Previous : Requirements Planning Matrix
Matrix Overview : "Tasks Performed by Role" for RAD Path
Stage Overview : User Design Stage
Overview : Table of Contents
This page was last built on May 01, 1997.