* Identify recipients of Post Implementation Assessment. The recipients may include both business and information technology management.
ð Updates deliverable D7.1 Post Implementation Assessment.
* Counsel application development team on PIA findings.
* Communicate PIA findings to the project's end users.
* Formulate adjustments to ADM.
ð Updates deliverable D7.1 Post Implementation Assessment.
* Advise methodology experts of Post Implementation Assessment findings.
* Publish Post Implementation Assessment.